SPMRM | Ministry of Rural Development | GOI
Statewise Progress against Convergence Scheme "Power"
Sl. No. State Name Total No. of Districts Covered Total No. of Clusters Covered Total No. of GPs Covered Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 11 11 68 32 24 8 1 23 24 36.45 26.64
Total 11 11 68 32 24 8 1 23 24 36.45 26.64
1 BIHAR 1 1 5 1 0 1 0 0 0 3.92 0.00
2 JAMMU AND KASHMIR 1 1 5 5 3 2 0 3 3 2.44 0.93
3 NAGALAND 2 2 9 5 0 5 0 0 0 3.72 0.00
4 PUNJAB 1 1 1 1 1 0 1 0 1 6.50 6.50
5 TAMIL NADU 1 1 5 1 1 0 0 1 1 1.83 1.83
6 TRIPURA 1 1 4 4 4 0 0 4 4 1.31 1.31
7 UTTAR PRADESH 4 4 39 15 15 0 0 15 15 16.73 16.07