SPMRM | Ministry of Rural Development | GOI
Statewise Progress against Convergence Scheme "NABARD Consultancy Services"
Sl. No. State Name Total No. of Districts Covered Total No. of Clusters Covered Total No. of GPs Covered Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 20 21 50 70 58 12 5 49 54 68.67 52.47
Total 20 21 50 70 58 12 5 49 54 68.67 52.47
1 ANDHRA PRADESH 4 4 8 9 9 0 2 7 9 20.18 20.08
2 HIMACHAL PRADESH 1 1 4 1 1 0 1 0 1 6.88 6.88
3 JHARKHAND 2 2 4 2 2 0 1 0 1 0.05 0.45
4 KARNATAKA 2 3 4 14 12 2 0 12 12 2.37 2.25
5 KERALA 1 1 1 5 5 0 0 2 2 6.87 2.11
6 MADHYA PRADESH 1 1 6 10 0 10 0 0 0 3.86 0.00
7 MAHARASHTRA 1 1 2 2 2 0 1 1 2 1.55 0.22
8 TAMIL NADU 4 4 9 9 9 0 0 9 9 10.05 5.30
9 TELANGANA 2 2 2 3 3 0 0 3 3 9.00 9.00
10 UTTAR PRADESH 1 1 3 1 1 0 0 1 1 0.06 0.06
11 UTTARAKHAND 1 1 7 14 14 0 0 14 14 7.79 6.12