SPMRM | Ministry of Rural Development | GOI
GP Progress against Convergence Scheme "Tribal Special Plan"
Sl. No. State Name District Name Cluster Name GP Name Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 40 40 0 9 31 40 34.80 33.90
Total 40 40 0 9 31 40 34.80 33.90
1 CHHATTISGARH MAHASAMUND BHNWARPUR KHOGSA 1 1 0 0 1 1 1.25 1.25
2 GUJARAT NAVSARI RUMLA AGASI 2 2 0 0 2 2 0.53 0.53
3 GUJARAT NAVSARI RUMLA GHOLAR 2 2 0 0 2 2 0.20 0.20
4 GUJARAT NAVSARI RUMLA MOGRAWADI 1 1 0 0 1 1 0.43 0.43
5 GUJARAT NAVSARI RUMLA RUMLA 6 6 0 0 6 6 0.86 0.86
6 GUJARAT VALSAD SANJAN SANJAN 2 2 0 0 2 2 28.56 28.56
7 KARNATAKA BALLARI MOKA MOKA 21 21 0 8 13 21 1.22 0.32
8 KARNATAKA BALLARI TORANGALLU TORANGAL 1 1 0 1 0 1 0.50 0.50
9 KARNATAKA RAICHUR GURUGUNTA GURUGUNTA 4 4 0 0 4 4 1.25 1.25