Geo Taged Work Details
WORK CODE
W-244-33-289-88619
WORK NAME
ELECTRIFICATION OF NEWLY CONSTRUCTED ANGANAWADIS UNDER RURBAN PROJECT
STATE
KERALA
CLUSTER
VELLANAD - ARYANAD CLUSTER
COMPONENT
SOCIAL WELFARE
SUBCOMPONENT
CONSTRUCTION/UPGRADATION OF ICDS CENTRES/ANGANWADI
GP
VELLANAD,
LAT:   
8.567323
LONG:    
77.0609213
STATUS:    
Ongoing
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-03-30 12:43:31
UPLOADED TIME:   
2023-03-30 15:17:04
DESCRIPTION:   
ongoing
LAT:   
8.5673028
LONG:    
77.0608795
STATUS:    
Ongoing
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-03-30 12:43:31
UPLOADED TIME:   
2023-03-30 15:17:04
DESCRIPTION:   
ongoing
LAT:   
8.5673205
LONG:    
77.0609004
STATUS:    
Completed
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-07-10 14:55:40
UPLOADED TIME:   
2023-07-12 10:56:35
DESCRIPTION:   
completed
LAT:   
8.5673118
LONG:    
77.0609309
STATUS:    
Completed
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-07-10 14:55:40
UPLOADED TIME:   
2023-07-12 10:56:35
DESCRIPTION:   
completed
LAT:   
8.5673205
LONG:    
77.0609004
STATUS:    
Completed
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-07-10 14:56:02
UPLOADED TIME:   
2023-07-12 10:56:39
DESCRIPTION:   
completed
LAT:   
8.5673118
LONG:    
77.0609309
STATUS:    
Completed
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-07-10 14:56:02
UPLOADED TIME:   
2023-07-12 10:56:39
DESCRIPTION:   
completed
LAT:   
8.5673019
LONG:    
77.0609602
STATUS:    
Completed
UPLOADED BY:   
DLNATHIRUVANANTHAPURAM
GP NAME:   
VELLANAD
CAPTURED TIME:   
2023-07-10 14:56:02
UPLOADED TIME:   
2023-07-12 10:56:39
DESCRIPTION:   
completed