Sl. No. State Name District Name Cluster Name GP Name Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 10 9 0 0 9 9 1.19 0.19
Total 10 9 0 0 9 9 1.19 0.19
1 KARNATAKA VIJAYANAGAR 114 DANAPURA 114.DANAPURA 6 6 0 0 6 6 0.16 0.14
2 KARNATAKA VIJAYANAGAR 114 DANAPURA KALLAHALLI 3 3 0 0 3 3 0.05 0.05
3 KARNATAKA RAICHUR GURUGUNTA GURUGUNTA 1 0 0 0 0 0 0.98 0.00