Sl. No. State Name District Name Total No. of Clusters Covered Total No. of GPs Covered Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 11 68 32 24 8 1 23 24 36.45 26.64
Total 11 68 32 24 8 1 23 24 36.45 26.64
1 BIHAR LAKHISARAI 1 5 1 0 1 0 0 0 3.92 0.00
2 JAMMU AND KASHMIR KUPWARA 1 5 5 3 2 0 3 3 2.44 0.93
3 NAGALAND KOHIMA 1 3 3 0 3 0 0 0 2.04 0.00
4 NAGALAND PEREN 1 6 2 0 2 0 0 0 1.68 0.00
5 PUNJAB GURDASPUR 1 1 1 1 0 1 0 1 6.50 6.50
6 TAMIL NADU KANNIYAKUMARI 1 5 1 1 0 0 1 1 1.83 1.83
7 TRIPURA NORTH TRIPURA 1 4 4 4 0 0 4 4 1.31 1.31
8 UTTAR PRADESH BAREILLY 1 12 1 1 0 0 1 1 1.52 1.52
9 UTTAR PRADESH MAHOBA 1 12 12 12 0 0 12 12 6.43 6.43
10 UTTAR PRADESH SHRAVASTI 1 10 1 1 0 0 1 1 3.26 2.60
11 UTTAR PRADESH SONBHADRA 1 5 1 1 0 0 1 1 5.53 5.53