Sl. No. State Name District Name Cluster Name Total No. of GPs Covered Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 68 87 71 16 3 9 6 25.25 3.94
Total 68 87 71 16 3 9 6 25.25 3.94
1 ASSAM BAKSA TAMULPUR RURBAN CLUSTER 4 2 0 2 0 0 0 1.76 0.00
2 ASSAM KAMRUP HAJO RURBAN CLUSTER 3 12 0 12 0 0 0 3.90 0.28
3 BIHAR GAYA TANKUPPA 1 1 1 0 0 0 0 0.63 0.00
4 GUJARAT PANCH MAHALS MORVA 11 1 1 0 0 1 1 0.08 0.08
5 HARYANA FATEHABAD SAMAIN 1 1 1 0 0 0 0 4.50 0.00
6 HARYANA PANIPAT SEWAH 9 1 1 0 0 0 0 1.25 0.00
7 HIMACHAL PRADESH CHAMBA SIHUNTA 1 1 1 0 1 0 1 0.07 0.01
8 HIMACHAL PRADESH MANDI AUT 6 8 8 0 0 1 1 1.04 0.00
9 JAMMU AND KASHMIR JAMMU GOLE GUJRAL 2 5 3 2 1 2 1 0.06 0.00
10 MADHYA PRADESH ALIRAJPUR INDARSING KI CHOWKI 2 4 4 0 0 4 0 0.02 0.02
11 MAHARASHTRA NAGPUR WADODA 1 1 1 0 0 0 0 0.05 0.00
12 TELANGANA JAYASHANKAR BHUPALAPALLY NAGARAM 1 1 1 0 0 0 0 5.40 1.40
13 TELANGANA NAGARKURNOOL VENNACHERLA 1 1 1 0 1 0 1 4.80 1.41
14 TELANGANA RANGA REDDY SHANKARPALLY 10 47 47 0 0 0 0 0.96 0.00
15 TRIPURA SOUTH TRIPURA HRISHYAMUKH 15 1 1 0 0 1 1 0.73 0.73