SPMRM | Ministry of Rural Development | GOI
Clusterwise Progress against Convergence Scheme "Power"
Sl. No. State Name District Name Cluster Name Total No. of GPs Covered Total No. of Works Total No. of Works Approved Total No. of Works Not Approved Total No. of Works Ongoing Total No. of Works Completed Total No. of Works Geotagged Total Investment (In Cr.) Total Expenditure (In Cr.)
Total 68 32 24 8 1 23 24 36.45 26.64
Total 68 32 24 8 1 23 24 36.45 26.64
1 BIHAR LAKHISARAI PIPARIYA 5 1 0 1 0 0 0 3.92 0.00
2 JAMMU AND KASHMIR KUPWARA KHUMRIYAL 5 5 3 2 0 3 3 2.44 0.93
3 NAGALAND KOHIMA KOHIMA SADAR 3 3 0 3 0 0 0 2.04 0.00
4 NAGALAND PEREN PEDI (NGWALWA) 6 2 0 2 0 0 0 1.68 0.00
5 PUNJAB GURDASPUR FATEHGARH CHURIAN 1 1 1 0 1 0 1 6.50 6.50
6 TAMIL NADU KANNIYAKUMARI CHADAYAMANGALAM 5 1 1 0 0 1 1 1.83 1.83
7 TRIPURA NORTH TRIPURA BELIANCHIP 4 4 4 0 0 4 4 1.31 1.31
8 UTTAR PRADESH BAREILLY URLA JAGIR 12 1 1 0 0 1 1 1.52 1.52
9 UTTAR PRADESH MAHOBA SRI NAGAR 12 12 12 0 0 12 12 6.43 6.43
10 UTTAR PRADESH SHRAVASTI CHAHALWA 10 1 1 0 0 1 1 3.26 2.60
11 UTTAR PRADESH SONBHADRA KODAI 5 1 1 0 0 1 1 5.53 5.53