Sl. No. State Name District Name Cluster Name Total No of Works Total No of Approved Works Total No of Not Approved Works Total No of Not Started Works Total No of Ongoing Works Total No of Completed Works Total No of Geotagged Works Percentage of Work Completion
Total 5210 3577 142 58 204 3315 3230
Total 5210 3577 142 58 204 3315 3230
1 KARNATAKA BELAGAVI KANGRALI 854 587 25 3 0 584 483 99.49 %
2 KARNATAKA BENGALURU URBAN HARAGADDE 1224 925 1 0 6 919 895 99.35 %
3 KARNATAKA VIJAYANAGAR 114 DANAPURA 936 821 6 43 24 754 712 91.84 %
4 KARNATAKA RAICHUR GURUGUNTA 263 233 26 1 27 205 207 87.98 %
5 KARNATAKA GADAG HULAKOTI 399 317 15 3 39 275 266 86.75 %
6 KARNATAKA VIJAYANAGAR HOLALU 831 430 12 7 59 364 405 84.65 %
7 KARNATAKA BALLARI TORANGALLU 230 93 14 0 17 76 93 81.72 %
8 KARNATAKA BALLARI MOKA 473 171 43 1 32 138 169 80.70 %