SPMRM | Ministry of Rural Development | GOI
Convergence Based Analytical Report at CLuster Level of JHARKHAND
Sl. Cluster name No of Convergence Works as per DPR Convergence FS Entered Works Convergence FS Amount
(₹ in Crore)
Convergence Expenditure Amount
(₹ in Crore)
Convergence Expenditure Percentage
(%)
Completed Works Completed Works
(%)
A B C D (D/C*100) E (E/B*100)
Total 2189 2151 1087.52 877.95 80.73 697 32.40
1 AIDEGA 72 72 66.25 50.67 76.48 44 61.11
2 BEHRABANK 91 91 44.72 40.00 89.43 22 24.18
3 BHANDARIDIH 351 353 66.96 53.95 80.57 98 27.76
4 BICHA 92 92 117.72 92.14 78.27 20 21.74
5 BIRHU 167 167 55.77 49.93 89.52 112 67.07
6 BRAMBE 194 195 42.70 37.06 86.79 14 7.18
7 DHARAMBAHAL 219 219 39.36 20.38 51.78 80 36.53
8 DUDHBILA 173 173 86.60 61.33 70.82 58 33.53
9 GAURIYA KARMA 110 110 153.26 129.86 84.74 50 45.45
10 ILAMI 69 69 47.83 34.49 72.10 26 37.68
11 KARAUNDI 152 116 99.22 74.44 75.03 19 16.38
12 MANGRA 96 89 47.37 36.76 77.59 38 42.70
13 PALANI 156 155 61.15 57.32 93.74 50 32.26
14 SARADHU 66 68 73.15 66.80 91.32 19 27.94
15 SIYALJORI 181 182 85.45 72.82 85.22 47 25.82
Total 2189 2151 1087.52 877.95 80.73 697 32.40